The building was constructed in 2013 with practical completion achieved on 19 August 2013. The building extends over seven floors with 146 guest bedrooms and ensuite facilities. Accommodation includes the main reception, communal toilets and staff areas to ground floor with guest bedrooms located on the upper floors. Plant rooms are located on the roof top and ground floor level.
The structural frame of the building is constructed in reinforced concrete with concrete ground and intermediate floors. The main roof comprises a warm deck roof construction weathered in a polymeric single ply roofing membrane laid over insulation. The external walls generally consist of cavity construction at ground level comprising external facing brick and internal concrete block work. The upper floors are provided with a ‘Sto’ external insulated cladding system with walls dry lined internally.
Fortress steel external door sets are located at the service entrance, ground floor lift lobby, roof top plant room and ground level plant rooms and the property has aluminium framed double glazed windows. Internally finishes typically comprise of suspended ceilings, plastered and painted walls, timber doors with laminated finish and a mix of carpet and vinyl floor coverings.
In terms of M&E the property is serviced by two 10 person lifts, heating and cooling is provided by a Variable Refrigerant Volume (VRV) air-conditioning system and hot water generated from 2 condensing gas fired boilers.
We understand the total gross internal floor area is approximately 38,100 sq ft (3,540 sq m).